How to Convert a Client to Project, or Phase to Project on Mosaic

By default, Mosaic maps the following Costpoint Project Levels to Mosaic Data Types:

Costpoint Data TypeMosaic Data Type
Level 1Client
Level 2Project
Level 3Phase
Level 4Subphase

Demote a Client (Costpoint Project Level 1) to become a Mosaic Project

  1. On Mosaic, go to Settings > Integrations > Costpoint
  2. Under the Clients tab, find the unlinked Client (Costpoint Project Level 1) that you wish to demote to a Project
  3. Select the Client and click Change to Project
3074
  1. Navigate to the Projects > Unlinked tab
  2. You should find the new Project listed under No Client

Promote a Phase (Costpoint Project Level 3) to become a Mosaic Project

  1. On Mosaic, go to Settings > Integrations > Costpoint
  2. Under the Projects tab, find the Phase that you wish to promote to a Project
  3. If the Project is linked, unlink the Project first

  1. Under Projects > Unlinked, click on the 3-dots next to the Phase and click Change to Project
  1. Refresh the page and navigate to the Projects > Unlinked tab
  2. You should find the new Project available for import